2016年ACCA F5真题及答案
Question:
Glove Co makes high quality,hand - made
gloves which it sells for an average of $180 per pair. The standard cost of
labour for each pair is $42 and the standard labour time for each pair is three
hours. In the last quarter,Glove Co had budgeted production of 12,000
pairs,although actual production was 12,600 pairs in order to meet demand.
37,000 hours were used to complete the work and there was no idle time. The
total labour cost for the quarter was $531,930.
At the beginning of the last quarter,the
design of the gloves was changed slightly. The new design required workers to
sew the company‘s logo on to the back of every glove made and the estimated
time to do this was 15 minutes for each pair. However,no - one told the
accountant responsible for updating standard costs that the standard time per
pair of gloves needed to be changed. Similarly,although all workers were given
a 2% pay rise at the beginning of the last quarter,the accountant was not told
about this either. Consequently,the standard was not updated to reflect these
changes.
When overtime is required,workers are paid
25% more than their usual hourly rate.
Required:
(a) Calculate the total labour rate and
total labour efficiency variances for the last quarter.
(b) Analyse the above total variances into
component parts for planning and operational variances in as much detail as the
information allows.
(c) Assess the performance of the production
manager for the last quarter.
Answer:
(a) Basic variances
Labour rate variance
Standard cost of labour per hour = $42/3 =
$14 per hour.
Labour rate variance = (actual hours paid x
actual rate) - (actual hours paid x std rate)
Actual hours paid x actual rate = $531,930.
Actual hours paid x std rate = 37,000 x $14
= $518,000.
Therefore rate variance = $531,930 -
$518,000 = $13,930 A
Labour efficiency variance
Labour efficiency variance = (actual
production in std hours - actual hours worked) x std rate
[(12,600 x 3) - 37,000] x $14 = $11,200 F
(b) Planning and operational variances
Labour rate planning variance
(Revised rate - std rate) x actual hours
paid = [$14·00 – ($14·00 x 1·02)] x 37,000 = $10,360 A.
Labour rate operational variance
Revised rate x actual hours paid =$14·28 x
37,000= $528,360.
Actual cost = $531,930.
Variance = $3,570 A.
Labour efficiency planning variance
(Standard hours for actual production - revised hours for actual production) x std
rate
Revised hours for each pair of gloves =
3·25 hours.
[37,800 – (12,600 x 3·25)] x $14 = $44,100
A.
Labour efficiency operational variance
(Revised hours for actual production -
actual hours for actual production) x std rate
(40,950 - 37,000) x $14 = $55,300 F.
(c) Analysis of performance
At a first glance,performance looks mixed
because the total labour rate variance is adverse and the total labour
efficiency variance is favourable. However,the operational and planning
variances provide a lot more detail on how these variances have occurred.
The production manager should only be held
accountable for variances which he can control. This means that he should only
be held accountable for the operational variances. When these operational
variances are looked at it can be seen that the labour rate operational
variance is $3,570 A. This means that the production manager did have to pay
for some overtime in order to meet demand but the majority of the total labour
rate variance is driven by the failure to update the standard for the pay rise
that was applied at the start of the last quarter. The overtime rate would also
have been impacted by that pay increase.
Then,when the labour efficiency operational
variance is looked at,it is actually $55,300 F. This shows that the production
manager has managed his department well with workers completing production more
quickly than would have been expected when the new design change is taken into
account. The total operating variances are therefore $51,730 F and so overall
performance is good.
The adverse planning variances of $10,360
and $44,100 do not reflect on the performance of the production manager and can
therefore be ignored here.