ACCA考试
报考指南考试报名准考证打印成绩查询考试题库

重置密码成功

请谨慎保管和记忆你的密码,以免泄露和丢失

注册成功

请谨慎保管和记忆你的密码,以免泄露和丢失

当前位置: 首页ACCA考试业绩管理(基础阶段)历年真题正文
2016年ACCA F5真题及答案
帮考网校2019-01-09 10:15
2016年ACCA F5真题及答案

Question:

Glove Co makes high quality,hand - made gloves which it sells for an average of $180 per pair. The standard cost of labour for each pair is $42 and the standard labour time for each pair is three hours. In the last quarter,Glove Co had budgeted production of 12,000 pairs,although actual production was 12,600 pairs in order to meet demand. 37,000 hours were used to complete the work and there was no idle time. The total labour cost for the quarter was $531,930.

At the beginning of the last quarter,the design of the gloves was changed slightly. The new design required workers to sew the company‘s logo on to the back of every glove made and the estimated time to do this was 15 minutes for each pair. However,no - one told the accountant responsible for updating standard costs that the standard time per pair of gloves needed to be changed. Similarly,although all workers were given a 2% pay rise at the beginning of the last quarter,the accountant was not told about this either. Consequently,the standard was not updated to reflect these changes.

When overtime is required,workers are paid 25% more than their usual hourly rate.

Required

(a) Calculate the total labour rate and total labour efficiency variances for the last quarter.

(b) Analyse the above total variances into component parts for planning and operational variances in as much detail as the information allows.

(c) Assess the performance of the production manager for the last quarter.

Answer:

(a) Basic variances

Labour rate variance

Standard cost of labour per hour = $42/3 = $14 per hour.

Labour rate variance = (actual hours paid x actual rate) - (actual hours paid x std rate)

Actual hours paid x actual rate = $531,930.

Actual hours paid x std rate = 37,000 x $14 = $518,000.

Therefore rate variance = $531,930 - $518,000 = $13,930 A

Labour efficiency variance

Labour efficiency variance = (actual production in std hours - actual hours worked) x std rate

[(12,600 x 3) - 37,000] x $14 = $11,200 F

(b) Planning and operational variances

Labour rate planning variance

(Revised rate - std rate) x actual hours paid = [$14·00 – ($14·00 x 1·02)] x 37,000 = $10,360 A.

Labour rate operational variance

Revised rate x actual hours paid =$14·28 x 37,000= $528,360.

Actual cost = $531,930.

Variance = $3,570 A.

Labour efficiency planning variance

(Standard hours for actual production  - revised hours for actual production) x std rate

Revised hours for each pair of gloves = 3·25 hours.

[37,800 – (12,600 x 3·25)] x $14 = $44,100 A.

Labour efficiency operational variance

(Revised hours for actual production - actual hours for actual production) x std rate

(40,950 - 37,000) x $14 = $55,300 F.

(c) Analysis of performance

At a first glance,performance looks mixed because the total labour rate variance is adverse and the total labour efficiency variance is favourable. However,the operational and planning variances provide a lot more detail on how these variances have occurred.

The production manager should only be held accountable for variances which he can control. This means that he should only be held accountable for the operational variances. When these operational variances are looked at it can be seen that the labour rate operational variance is $3,570 A. This means that the production manager did have to pay for some overtime in order to meet demand but the majority of the total labour rate variance is driven by the failure to update the standard for the pay rise that was applied at the start of the last quarter. The overtime rate would also have been impacted by that pay increase.

Then,when the labour efficiency operational variance is looked at,it is actually $55,300 F. This shows that the production manager has managed his department well with workers completing production more quickly than would have been expected when the new design change is taken into account. The total operating variances are therefore $51,730 F and so overall performance is good.

The adverse planning variances of $10,360 and $44,100 do not reflect on the performance of the production manager and can therefore be ignored here.

声明:本文内容由互联网用户自发贡献自行上传,本网站不拥有所有权,未作人工编辑处理,也不承担相关法律责任。如果您发现有涉嫌版权的内容,欢迎发送邮件至:service@bkw.cn 进行举报,并提供相关证据,工作人员会在5个工作日内联系你,一经查实,本站将立刻删除涉嫌侵权内容。
测一测是否符合报考条件
免费测试,不要错过机会
提交
互动交流

微信扫码关注公众号

获取更多考试热门资料

温馨提示

信息提交成功,稍后帮考专业顾问免费为您解答,请保持电话畅通!

我知道了~!
温馨提示

信息提交成功,稍后帮考专业顾问给您发送资料,请保持电话畅通!

我知道了~!

提示

信息提交成功,稍后班主任联系您发送资料,请保持电话畅通!